Alki Project Update 9-15-15

Crestline Builders LLC has been making steady progress on the 63rd Ave SW Townhomes just off of Alki Beach in Seattle, WA. The project consists of 3 separate buildings totaling 7 residential units. In the last several weeks the site has been cleared, excavation has been completed. We also have done a new sewer line using a trenchless technology as to not disturb the road and impede traffic.

With the sewer lining completed and excavation done for the time being, we have moved onto forming the foundation for 2 of the 3 buildings. Due to the size of the property, we have to do the foundations in 2 stages as the dirt has to be staged in the location of the 3rd building on the site. 

We will keep you posted as vertical construction starts moving forward on this fantastic project in Seattle, WA.

Pidgeon Point foundation progress

After the foundation footings were poured, Crestline Builders LLC has been making good progress on the Pidgeon Point project in West Seattle. Forming and reinforcement placement for the foundation walls is complete and the foundation concrete will be poured later this week. Crestline Builders LLC has extensive experience in building projects on steep slopes and critical areas.